Co-Generation

WEBVTT
Kind: captions
Language: en

00:00:00.149
today we will discuss about coal
00:00:02.119 00:00:02.129 generation process also called in short
00:00:05.390 00:00:05.400 from CHP what is cogeneration
00:00:08.680 00:00:08.690 cogeneration refers to the system of
00:00:11.209 00:00:11.219 producing both power and process heat
00:00:13.660 00:00:13.670 the system is so designed that it meets
00:00:16.760 00:00:16.770 the requirements both for thermal energy
00:00:19.099 00:00:19.109 and mechanical energy from a single
00:00:21.500 00:00:21.510 primary energy source firstly we will
00:00:24.050 00:00:24.060 discuss about the parts of the whole
00:00:25.700 00:00:25.710 generation we have steam and water drum
00:00:28.750 00:00:28.760 in which team will be prepared for the
00:00:31.400 00:00:31.410 further working and a back pressure
00:00:34.100 00:00:34.110 turbine in the back pressure steam
00:00:37.069 00:00:37.079 turbine the steam leaves the turbine at
00:00:39.830 00:00:39.840 a pressure which is appropriate to
00:00:41.840 00:00:41.850 process steam requirement 30d super
00:00:46.459 00:00:46.469 heater what is the super heater the
00:00:49.340 00:00:49.350 super heater used extracted heat from
00:00:51.979 00:00:51.989 the turbine and use this heat for the
00:00:54.709 00:00:54.719 further purpose this is a process were
00:00:59.630 00:00:59.640 unit in which reheat is used for
00:01:04.280 00:01:04.290 processing the work in this unit we can
00:01:07.520 00:01:07.530 heating we can take cooling we can take
00:01:10.850 00:01:10.860 anything from the extraction of heat
00:01:13.450 00:01:13.460 which is coming from the super heater
00:01:18.940 00:01:18.950 the super heater has a pipe for water
00:01:22.429 00:01:22.439 which will supply water and the
00:01:25.460 00:01:25.470 extracted heat will be mixed with the
00:01:27.560 00:01:27.570 water and converted into saturated steam
00:01:31.300 00:01:31.310 this is the pump for pumping the
00:01:34.390 00:01:34.400 condensate to the steam and water drum
00:01:37.249 00:01:37.259 and all the connecting pipes now we see
00:01:40.640 00:01:40.650 the working of the whole generation with
00:01:43.130 00:01:43.140 the help of back pressure turbine what
00:01:46.399 00:01:46.409 will happen steam will come from the
00:01:49.999 00:01:50.009 steam and water drum and reach on the
00:01:53.480 00:01:53.490 turbine back pressure turbine and it
00:01:56.569 00:01:56.579 will work on the turbine turbine will
00:01:59.780 00:01:59.790 start rotating and extracted steam after
00:02:04.999 00:02:05.009 doing work in the turbine reach on the D
00:02:08.839 00:02:08.849 super heater where this will mix with
00:02:13.040 00:02:13.050 the
00:02:13.400 00:02:13.410 butter and convert in the saturated
00:02:17.540 00:02:17.550 steam and this saturated steam will
00:02:20.990 00:02:21.000 reach the process work unit here this
00:02:24.200 00:02:24.210 saturated steam can be used for drying
00:02:26.360 00:02:26.370 for heating for pulling purpose anything
00:02:29.450 00:02:29.460 we can use there of saturated steam then
00:02:34.460 00:02:34.470 after working after take whole work from
00:02:37.700 00:02:37.710 the saturated steam this condensate will
00:02:42.320 00:02:42.330 go to the pump and pump will pump this
00:02:45.500 00:02:45.510 condensate to the steam and water drop
00:02:47.770 00:02:47.780 this is the back pressure turbine unit
00:02:50.600 00:02:50.610 cogeneration will also in extraction
00:02:55.100 00:02:55.110 steam turbine there will be extraction
00:02:58.010 00:02:58.020 steam turbine instead of back pressure
00:03:00.410 00:03:00.420 turbine what is extraction steam turbine
00:03:03.470 00:03:03.480 we can extract directly from praveen
00:03:07.460 00:03:07.470 casing and this steam will go to the
00:03:11.180 00:03:11.190 process work and some steam which will
00:03:14.960 00:03:14.970 work on the turbine will go in the
00:03:18.110 00:03:18.120 condenser so there are two separate unit
00:03:21.470 00:03:21.480 first a direct extraction steam will go
00:03:24.740 00:03:24.750 to the process work and the steam which
00:03:27.590 00:03:27.600 will do work directly go to the
00:03:29.750 00:03:29.760 condenser now we see the working of
00:03:32.770 00:03:32.780 extraction steam turbine cogeneration
00:03:34.910 00:03:34.920 process steam will come from the steam
00:03:38.960 00:03:38.970 and water drum and turbine will start
00:03:41.750 00:03:41.760 working some steam after working will go
00:03:45.770 00:03:45.780 to the condenser and some steam will go
00:03:49.699 00:03:49.709 to the process where this team have high
00:03:54.620 00:03:54.630 efficiency or high heating steam will go
00:03:57.920 00:03:57.930 to the process work unit there we can
00:04:00.290 00:04:00.300 use this heat for heating cooling or
00:04:02.390 00:04:02.400 anything we want then this heat this
00:04:08.870 00:04:08.880 condensate will go to the pump and also
00:04:12.199 00:04:12.209 from the condenser condensate will go to
00:04:15.229 00:04:15.239 the pump and pump will pump this
00:04:18.050 00:04:18.060 00:04:20.000 00:04:20.010 so this is the extraction steam turbine
00:04:22.909 00:04:22.919 cogeneration process so this is the
00:04:26.120 00:04:26.130 cogeneration
00:04:27.230 00:04:27.240 process from which we can take both
00:04:29.540 00:04:29.550 mechanical and thermal energy we can use
00:04:33.290 00:04:33.300 all of our heat with efficient manner
00:04:37.040 00:04:37.050 thank you for seeing this video for more
00:04:39.559 00:04:39.569 updated videos you can subscribe me on
00:04:41.749 00:04:41.759 my channel learn and grow thank you
Office location
Engineering company LOTUS®
Russia, Ekaterinburg, Lunacharskogo street, 240/12

Phone: +7 343 216 77 75

E-mail: info@lotus1.ru

Sales phone

Russia: +7 343 216 77 75

WhatsApp: +79122710308