How to Read Process Flow Diagrams (PFDs_PFS) - A Complete Tutorial

WEBVTT
Kind: captions
Language: en

00:00:01.710
[Music]
00:00:08.350 00:00:08.360 welcome to hearted engineer calm I am
00:00:11.680 00:00:11.690 Warren Patel in this video you will
00:00:14.440 00:00:14.450 learn about process flow diagram which
00:00:16.840 00:00:16.850 is also known as process flowchart
00:00:18.580 00:00:18.590 process flow shapes and process flow
00:00:21.339 00:00:21.349 scheme I will explain you how to read
00:00:24.760 00:00:24.770 this P of T or P FS with the help of
00:00:28.060 00:00:28.070 real time PFD is the base document that
00:00:32.620 00:00:32.630 used to develop more complex P&ID
00:00:35.729 00:00:35.739 if you want to master P&ID you must
00:00:39.850 00:00:39.860 master the PFD so please watch the video
00:00:43.150 00:00:43.160 till then please subscribe to my channel
00:00:46.619 00:00:46.629 because it helps me to increase my reach
00:00:49.630 00:00:49.640 on YouTube and you will also get regular
00:00:52.509 00:00:52.519 updates on your video so subscribe now
00:00:56.130 00:00:56.140 what is process flow diagram process
00:00:59.919 00:00:59.929 flow diagram is a simple drawing that
00:01:02.470 00:01:02.480 shows the relationship between major
00:01:05.020 00:01:05.030 equipment in process plant using
00:01:07.899 00:01:07.909 equipment symbols and shows the primary
00:01:10.960 00:01:10.970 process flow path of a unit you can
00:01:14.260 00:01:14.270 visualize the flow of material within
00:01:16.900 00:01:16.910 the plant with the help of this drawing
00:01:20.160 00:01:20.170 what is the use of PFD a process flow
00:01:23.950 00:01:23.960 diagram provides a quick overview of
00:01:26.710 00:01:26.720 entire operating unit or a system a
00:01:30.390 00:01:30.400 technician or engineer can use this
00:01:34.090 00:01:34.100 document to trace the flow of the
00:01:36.040 00:01:36.050 material through the unit the flow
00:01:39.520 00:01:39.530 diagram is also used for the visitor
00:01:42.310 00:01:42.320 information and new employee training it
00:01:45.580 00:01:45.590 is one of the core document to draw the
00:01:48.040 00:01:48.050 plot pant and P&ID what information does
00:01:52.570 00:01:52.580 PFD provide a typical PFD will include
00:01:57.040 00:01:57.050 all major equipment each equipment shown
00:02:00.760 00:02:00.770 on PFD has a unique equipment number and
00:02:03.700 00:02:03.710 a descriptive name it also shows main
00:02:07.480 00:02:07.490 dimension capacity and operating
00:02:10.059 00:02:10.069 information of the equipment
00:02:13.280 00:02:13.290 second is process flow stream or
00:02:15.170 00:02:15.180 interconnected piping PFD follows
00:02:19.280 00:02:19.290 left-right approach for the process flow
00:02:21.640 00:02:21.650 that means any process stream enter or
00:02:26.089 00:02:26.099 exit either from right or left however
00:02:29.030 00:02:29.040 please note that this left/right
00:02:31.610 00:02:31.620 approach is not a mandatory requirement
00:02:33.949 00:02:33.959 but good engineering practice all
00:02:37.399 00:02:37.409 process flow stream shown on PFD
00:02:40.039 00:02:40.049 will have a identification number a
00:02:42.280 00:02:42.290 description of the process condition and
00:02:44.869 00:02:44.879 chemical composition of each stream such
00:02:48.589 00:02:48.599 as pressure temperature density mass
00:02:51.860 00:02:51.870 flow rate and mass energy balance will
00:02:55.220 00:02:55.230 included in PMT this data will be either
00:02:58.909 00:02:58.919 displayed directly on PFD or included in
00:03:02.750 00:03:02.760 the flow summary table sometime it also
00:03:06.949 00:03:06.959 shown minimum normal and maximum value
00:03:10.129 00:03:10.139 of this process parameters next is
00:03:13.720 00:03:13.730 process flow direction of all process
00:03:16.490 00:03:16.500 line control wall and process critical
00:03:20.000 00:03:20.010 wall major bypass and recirculation
00:03:23.330 00:03:23.340 system and connection with other system
00:03:27.699 00:03:27.709 what is not included in PFT
00:03:31.809 00:03:31.819 pipe glass and pipeline numbers process
00:03:35.170 00:03:35.180 control instruments minor bypass wall
00:03:38.670 00:03:38.680 isolation and sort of wall maintenance
00:03:42.099 00:03:42.109 vents and drains relief walls and safety
00:03:45.699 00:03:45.709 walls and code class information you
00:03:50.949 00:03:50.959 must be thinking if this information are
00:03:53.410 00:03:53.420 not here then where they are
00:03:55.890 00:03:55.900 well these informations are covered in
00:03:59.440 00:03:59.450 P&ID which is more complex time than P
00:04:02.289 00:04:02.299 of T you will learn about PID in next
00:04:05.559 00:04:05.569 video to read PFD PF s pn ID p FS iso
00:04:11.020 00:04:11.030 and j drawing knowing the various symbol
00:04:14.470 00:04:14.480 for equipment wall and instrument is a
00:04:17.560 00:04:17.570 must so if you have not watched the
00:04:20.560 00:04:20.570 earlier video on P&ID PFD symbols please
00:04:24.219 00:04:24.229 watch that video first link is given in
00:04:27.010 00:04:27.020 the description
00:04:29.340 00:04:29.350 now look at this PFS or PFD well both
00:04:33.540 00:04:33.550 are same you can see the PFS of Oh a
00:04:36.990 00:04:37.000 small part of plant fuel oil and slope
00:04:39.450 00:04:39.460 tank
00:04:41.240 00:04:41.250 let's check the equipment that are using
00:04:44.130 00:04:44.140 this system
00:04:46.399 00:04:46.409 here you can see the tank pumps
00:04:51.219 00:04:51.229 exchanger vessel strainer and jet
00:04:57.499 00:04:57.509 mixture on the top of any PFD you can
00:05:02.779 00:05:02.789 see the list of all the major equipment
00:05:04.790 00:05:04.800 along with its size and capacity
00:05:09.350 00:05:09.360 all the main process lines are shown as
00:05:12.350 00:05:12.360 a dark black line and the theme black
00:05:14.659 00:05:14.669 line are minor process line arrowheads
00:05:18.110 00:05:18.120 on the line show the direction of the
00:05:20.629 00:05:20.639 flow fuel oil is coming from the other
00:05:23.899 00:05:23.909 is bail unit you can see the incoming
00:05:27.200 00:05:27.210 arrow with a dark head
00:05:29.469 00:05:29.479 if there is no dark hair and a simple
00:05:32.659 00:05:32.669 arrow is there like this it means the
00:05:36.200 00:05:36.210 line is coming from the same unit you
00:05:39.499 00:05:39.509 can see the battery limit between OS
00:05:41.179 00:05:41.189 bail and eyes bill this flow system is
00:05:44.570 00:05:44.580 numbered as a 1/4 which detail is given
00:05:47.779 00:05:47.789 in the table below square box with the
00:05:51.170 00:05:51.180 number inside will give you the process
00:05:54.050 00:05:54.060 stream number square box with later
00:05:57.499 00:05:57.509 inside means it refers to other service
00:06:01.159 00:06:01.169 and for the detail of that stream you
00:06:04.580 00:06:04.590 have to refer to the PFD of that process
00:06:07.570 00:06:07.580 here SL means team line and sale means
00:06:11.929 00:06:11.939 condensate line this is generic symbol
00:06:15.230 00:06:15.240 of wall if you want to know the exact
00:06:18.379 00:06:18.389 type of the wall you have to check the
00:06:20.390 00:06:20.400 P&ID then laters NC means normally
00:06:24.890 00:06:24.900 closed that means this wall remained
00:06:28.459 00:06:28.469 closed during normal operation now look
00:06:32.300 00:06:32.310 at this clue
00:06:33.730 00:06:33.740 this is circulation loop fuel oil from
00:06:38.059 00:06:38.069 the tank is supplied to the pump which
00:06:41.659 00:06:41.669 is passed through the heat exchanger and
00:06:43.670 00:06:43.680 returned to the tank you have to
00:06:46.969 00:06:46.979 maintain the temperature of the fuel oil
00:06:48.920 00:06:48.930 otherwise it will get thick and chalk
00:06:52.010 00:06:52.020 the line and also settle in the tank you
00:06:55.149 00:06:55.159 can see that there are two control wall
00:06:58.279 00:06:58.289 are shown in this loop one will maintain
00:07:01.249 00:07:01.259 the temperature by controlling the steam
00:07:03.350 00:07:03.360 and the second will maintain the flow
00:07:06.159 00:07:06.169 the symbols of the wall is generic
00:07:09.200 00:07:09.210 symbol of the remotely actuated wall it
00:07:12.409 00:07:12.419 can be hydraulic pneumatic or motor
00:07:15.320 00:07:15.330 operated type if you are interested in
00:07:19.010 00:07:19.020 learning more about wall and their
00:07:21.139 00:07:21.149 function you can buy
00:07:23.119 00:07:23.129 my full course on the wall in which I
00:07:25.760 00:07:25.770 have got more than 18 types of wall yes
00:07:29.809 00:07:29.819 this is marketing because that is how I
00:07:32.359 00:07:32.369 earn money to produce the good quality
00:07:34.699 00:07:34.709 videos so please support by purchasing
00:07:37.549 00:07:37.559 my course now back to our PFT see this
00:07:42.559 00:07:42.569 detail of pump recycle pump has a head
00:07:46.249 00:07:46.259 of 60 meters and the plant fuel oil has
00:07:49.159 00:07:49.169 a head of 216 meters this must be a huge
00:07:54.229 00:07:54.239 come let's look where they are on PFD
00:07:58.959 00:07:58.969 let me adjust the PFD on the screen so
00:08:01.969 00:08:01.979 that we can conclude our video
00:08:03.559 00:08:03.569 oh these pumps are turbine driven that
00:08:08.809 00:08:08.819 means these are critical pumps normally
00:08:12.320 00:08:12.330 turbine driven pumps are provided where
00:08:15.199 00:08:15.209 you want to run the pump even if there
00:08:17.839 00:08:17.849 is a total power failure in your plant
00:08:20.290 00:08:20.300 here we have a 2 basket strainer one on
00:08:24.350 00:08:24.360 a suction side and other on a pump
00:08:26.329 00:08:26.339 discharge side and we also have a heat
00:08:29.629 00:08:29.639 exchanger to maintain the temperature of
00:08:31.639 00:08:31.649 the fuel oil the suction strainer will
00:08:35.149 00:08:35.159 protect the pump impeller from any
00:08:37.100 00:08:37.110 foreign object that can damage the pump
00:08:39.499 00:08:39.509 and the discharge strainer will ensure
00:08:42.860 00:08:42.870 the clean supply to the user unit you
00:08:46.460 00:08:46.470 can see the temperature control loop
00:08:48.139 00:08:48.149 also here you can see the battery limit
00:08:53.030 00:08:53.040 of ice volando SPL fuel oil is supplied
00:08:56.809 00:08:56.819 to various ice value in its furnaces on
00:09:00.590 00:09:00.600 is Bill sight
00:09:02.030 00:09:02.040 you can see that one pressure control
00:09:04.400 00:09:04.410 wall is given which ensure constant
00:09:08.360 00:09:08.370 pressure in the fuel oil loop now let's
00:09:12.199 00:09:12.209 look at this trim table lots of process
00:09:16.939 00:09:16.949 parameter such as pressure temperature
00:09:19.720 00:09:19.730 flow rate and other details are given in
00:09:22.790 00:09:22.800 this table have a look on it
00:09:27.079 00:09:27.089 this is all about PMT you have learned
00:09:30.199 00:09:30.209 almost all detail that PFD provides in
00:09:34.340 00:09:34.350 next video I will explain you about the
00:09:36.650 00:09:36.660 P&ID visit my website hotter than zero
00:09:39.889 00:09:39.899 comm to download free study materials
00:09:42.230 00:09:42.240 and don't forget to subscribe my channel
00:09:44.389 00:09:44.399 to get regular updates on your video and
00:09:46.869 00:09:46.879 also like and share my video with your
00:09:49.549 00:09:49.559 friends if you want to request a video
00:09:51.889 00:09:51.899 please write in the comment see you soon
00:09:54.650 00:09:54.660 good bye
00:09:55.160 00:09:55.170 take care
Office location
Engineering company LOTUS®
Russia, Ekaterinburg, Lunacharskogo street, 240/12

Phone: +7 343 216 77 75

E-mail: info@lotus1.ru

Sales phone

Russia: +7 343 216 77 75

WhatsApp: +79122710308